Hoover Middle School


Upcoming Projects


 

CAMPUSWIDE RENOVATION

Comprehensive renovations to include new heating, ventilation and air conditioning system and select priority projects from LBUSD’s 2022 Facility Master Plan.

Construction starts: 2025-26
Projected completion: 2027-28

 

 

All-weather sports field

All-Weather Field

New all-weather sports field designed to maximize playability and safety. The field’s permeable turf will drain quickly in wet weather, increasing play time.  

Construction starts: 2027-28
Projected completion: 2028-29
 

 

Additional Renovations

Project

Description

Projected Start

Projected Completion

Safety & security upgrades Improvements that enhance school safety. Q4 - 2023 Q4 - 2023
Bottle filling stations New combined drinking fountain and bottle filling station. Q2 - 2024 Q3 - 2024
Paving repairs - Phase 1 Repair or replacement of asphalt and other outdoor surfaces. Q3 - 2024 Q3 - 2024
Painting New paint for existing buildings. Q3 - 2025 Q2 - 2026
Plumbing Repair or replacement of existing plumbing system. Q3 - 2025 Q2 - 2026
Paving repairs - Phase 2 Repair or replacement of asphalt and other outdoor surfaces. Q3 - 2026 Q3 - 2026

          Project list updated November 2023                   
          Q1 = Jan-Mar  Q2 = Apr-Jun  Q3 = Jul-Sep  Q4 = Oct-Dec

Completed Projects