Gompers Elementary School

Gompers Elementary School in Long Beach

Current Project


 

Heating, Ventilation & Air Conditioning 

New energy-efficient heating, ventilation and air conditioning (HVAC) systems for the school’s existing permanent buildings. HVAC systems help create safe and comfortable learning environments by maintaining comfortable temperatures and enhancing indoor air quality.

Additional school improvements include:

  • New audiovisual systems with overhead projectors & screens
  • New flooring, ceilings, lighting and paint
  • Window replacement or repair
  • Accessibility upgrades
  • Fire alarm system upgrades
  • Other renovations

Projected completion: Summer 2025

 

 

HVAC
Additional Renovations

Project

Description

Projected Start

Projected Completion

Painting New paint for existing buildings. Q3 - 2023 Q2 - 2024
Furniture replacement Modern, versatile furniture in all classrooms. Q4 - 2023 Q1 - 2024
Playground repairs Replacement of existing playground matting and play structures Q4 - 2023 Q4 - 2023
Roofing - Phase 1 Repair or replacement of existing building roofs. Q3 - 2024 Q3 - 2024
Paving repairs Repair or replacement of asphalt and other outdoor surfaces. Q3 - 2025 Q3 - 2025
Roofing - Phase 2  Repair or replacement of existing building roofs. Q3 - 2025 Q3 - 2025

          Project list updated November 2023                   
          Q1 = Jan-Mar  Q2 = Apr-Jun  Q3 = Jul-Sep  Q4 = Oct-Dec