Whittier Elementary School

Upcoming Project


 

CAMPUSWIDE RENOVATION 

Whittier's comprehensive renovations will include new energy-efficient heating, ventilation and air conditioning system for the school’s existing permanent buildings and select priority projects from LBUSD’s 2022 Facility Master Plan.

Additional campus improvements include:

  • New audiovisual systems with overhead projectors & screens
  • New flooring, ceilings, lighting and paint
  • Window replacement or repair
  • Accessibility upgrades
  • Fire alarm system upgrades
  • Other renovations
Construction starts: 2027-28
Projected completion: 2028-29

 

 

Construction worker preparing to add acoustical tiles to classroom ceiling.
Additional Renovations

Project

Description

Projected Start

Projected Completion

Paving repairs Repair or replacement of asphalt and other outdoor surfaces. Q3 - 2023 Q4 - 2023
Fencing New perimeter fencing. Q3 - 2023 Q4 - 2023
Playground repairs Replacement of existing playground matting and play structures Q3 - 2023 Q4 - 2023
Phone system upgrade New phone system for enhanced school safety and staff connectivity.  Q4 - 2023 Q4 - 2023
Bottle filling stations New combined drinking fountain and bottle filling station. Q1 - 2024 Q2 - 2024
Furniture replacement Modern, versatile furniture in all classrooms. Q2 - 2024 Q3 - 2024

          Project list updated November 2023                   
          Q1 = Jan-Mar  Q2 = Apr-Jun  Q3 = Jul-Sep  Q4 = Oct-Dec

Completed Projects