Signal Hill Elementary School
Upcoming Project
CAMPUSWIDE RENOVATION
Signal Hill Elementary's comprehensive renovations will include new energy-efficient heating, ventilation and air conditioning system for the school’s existing permanent buildings and select priority projects from LBUSD’s 2022 Facility Master Plan.
Additional campus improvements include:
- New audiovisual systems with overhead projectors & screens
- New flooring, ceilings, lighting and paint
- Window replacement or repair
- Accessibility upgrades
- Fire alarm system upgrades
- Other renovations
Construction starts: 2029-30
Projected completion: 2030-31
Additional Renovations
Project |
Description |
Projected Start |
Projected Completion |
---|---|---|---|
Skateboard racks | Stores and secures up to 14 skateboards per rack. | Q3 - 2023 | Q3 - 2023 |
Phone system upgrade | New phone system for enhanced school safety and staff connectivity. | Q4 - 2023 | Q4 - 2023 |
Furniture replacement | Modern, versatile furniture in all classrooms. | Q4 - 2023 | Q1 - 2024 |
Shade structure | Free-standing shade structure and matching picnic bench. | Q1 - 2024 | Q3 - 2024 |
Bottle filling stations | New combined drinking fountain and bottle filling station. | Q1 - 2024 | Q2 - 2024 |
Project list updated June 2023
Q1 = Jan-Mar Q2 = Apr-Jun Q3 = Jul-Sep Q4 = Oct-Dec