Riley Elementary School

Upcoming Project


 

SOLAR CANOPY

New solar canopy projected to meet approximately 85% of the school’s energy needs. Canopy may be stationed on the school’s playground, parking lot or field, sheltering students from sunlight and rain while generating clean energy.  

Construction starts: Q1 2025
Projected completion: Q2 2025

 

 

Additional Renovations

Project

Description

Projected Start

Projected Completion

Bottle filling stations New combined drinking fountain and bottle filling station. Q2 - 2024 Q3 - 2024
Playground repairs Replacement of existing playground matting and play structures Q4 - 2024 Q4 - 2024

          Project list updated November 2023                   
          Q1 = Jan-Mar  Q2 = Apr-Jun  Q3 = Jul-Sep  Q4 = Oct-Dec