MacArthur Elementary School
Upcoming Project
SOLAR CANOPY
New solar canopy projected to meet approximately 85% of the school’s energy needs. Canopy may be stationed on the school’s playground, parking lot or field, sheltering students from sunlight and rain while generating clean energy.
Construction starts: 2024-25
Projected completion: 2025-26
Additional Renovations
Project |
Description |
Projected Start |
Projected Completion |
---|---|---|---|
Paving repairs - Phase 1 | Repair or replacement of asphalt and other outdoor surfaces. | Q3 - 2023 | Q3 - 2023 |
Bottle filling stations | New combined drinking fountain and bottle filling station. | Q4 - 2023 | Q1 - 2024 |
Shade structure | Free-standing shade structure and matching picnic bench. | Q1 - 2024 | Q3 - 2024 |
Furniture replacement | Modern, versatile furniture in all classrooms. | Q1 - 2024 | Q2 - 2024 |
Playground repairs - Kindergarten | Replacement of existing playground matting and play structures | Q2 - 2024 | Q2 - 2024 |
Playground repairs - Secondary | Replacement of existing playground matting and play structures | Q4 - 2024 | Q4 - 2024 |
Paving repairs - Phase 2 | Repair or replacement of asphalt and other outdoor surfaces. | Q3 - 2027 | Q3 - 2027 |
Project list updated June 2023
Q1 = Jan-Mar Q2 = Apr-Jun Q3 = Jul-Sep Q4 = Oct-Dec
Completed Projects
- Phone System Upgrades
- Backpack Hooks
- Wi-Fi
- Safety & Security Upgrades
- Heating, Ventilation & Air Conditioning
- Intercom & Clock System Replacement
- Portable(s) Removal