Harte Elementary School
Upcoming Projects
Project |
Description |
Projected Start |
Projected Completion |
---|---|---|---|
Bottle filling stations | New combined drinking fountain and bottle filling station. | Q4 - 2023 | Q1 - 2024 |
Playground repairs | Replacement of existing playground matting and play structures | Q1 - 2024 | Q1 - 2024 |
Shade structure | Free-standing shade structure and matching picnic bench. | Q1 - 2024 | Q3 - 2024 |
HVAC maintenance - Phase 1 | Repairs to existing HVAC systems. | Q3 - 2024 | Q3 - 2024 |
Painting | New paint for existing buildings. | Q3 - 2024 | Q3 - 2024 |
Roofing - Phase 1 | Repair or replacement of existing building roofs. | Q3 - 2024 | Q3 - 2024 |
HVAC maintenance - Phase 2 | Repairs to existing HVAC systems. | Q3 - 2025 | Q3 - 2025 |
Roofing - Phase 2 | Repair or replacement of existing building roofs. | Q3 - 2025 | Q3 - 2025 |
Project list updated November 2023
Q1 = Jan-Mar Q2 = Apr-Jun Q3 = Jul-Sep Q4 = Oct-Dec
Completed Projects
- Furniture Replacement
- Skateboard Racks
- Backpack Hooks
- Phone System Upgrades
- Safety & Security Upgrades
- Wi-Fi
- Intercom & Clock System Replacement
- Portable(s) Removal