Cleveland Elementary School
Upcoming Projects
Project |
Description |
Projected Start |
Projected Completion |
---|---|---|---|
Bottle filling stations | New combined drinking fountain and bottle filling station. | Q2 - 2024 | Q3 - 2024 |
Playground repairs | Replacement of existing playground matting and play structures. | Q3 - 2024 | Q3 - 2024 |
Project list updated November 2023
Q1 = Jan-Mar Q2 = Apr-Jun Q3 = Jul-Sep Q4 = Oct-Dec
Completed Projects
- Paving Repairs
- Phone System Upgrade
- Skateboard Racks
- Shade Structure
- Furniture Replacement
- Backpack Hooks
- Wi-Fi
- Heating, Ventilation & Air Conditioning
- Fire Alarm Upgrade
- Intercom & Clock System Replacement
- Portable(s) Removal
- Core Switch & UPS Replacement