Skip To Main Content
Long Beach Downtown

Schools

Main Menu

Quarterly Bond Project Updates

1761 Walnut Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project entails the renovation of all campus buildings, including demolition of the existing TK/K building and four portables and the addition of a new TK/K building. It includes new HVAC systems in classrooms, offices, and key areas such as the auditorium, cafeteria, and kitchen, along with accessibility upgrades, necessary utility improvements, and the replacement of building finishes such as ceilings, flooring, painting, and lighting. The scope also includes campus-wide tactile signage, fire alarm system upgrades, and seismic enhancements where required by DSA standards. In addition, Measure Q improvements are incorporated, including enhanced colored paving, a new real turf play field, and new trees.

Washington Middle School | Transformation Q3 2025-2026

1450 Cedar Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project involves demolishing the entire middle school campus and constructing a completely new facility. The new campus will feature an auditorium, classrooms, a gymnasium, science labs, a state-of-the-art engineering building, new basketball courts, the first underground parking structure and a new turf soccer field.

Stevenson Elementary School | Modernization Plus Q3 2025-2026

Artist Renderings, Subject to Change

515 Lime Ave, Long Beach, CA 90802 

PROJECT OVERVIEW

Scope of Work: This project includes the replacement of existing HVAC system, which dates back to the 1990s, with a new, energy-efficient system. Accessibility will be improved with the installation of a new elevator, providing access to both two-story buildings in compliance with current accessibility standards. Additionally, classrooms will be renovated to meet current FDS standards, incorporating new projectors, markerboards, ceilings, lighting, paint and floor finishes to enhance the learning environment.

Sato Academy of Mathematics & Science | Heating, Ventilation and Air Conditioning (HVAC) Plus Q3 2025-2026

1100 Iroquois Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project includes significant mechanical, utility, and facility upgrades. Key improvements involve the installation of HVAC, upgrades to the utility infrastructure, and replacement of the fire alarm and electrical systems. Accessibility will be enhanced campus-wide, with specific focus on improvements within the auditorium, cafeteria, and kitchen. The project also covers the installation of new interior teaching and presentation tools, including projectors, screens, marker/tack boards, and AV systems. Finally, the existing natural turf field will be converted to a new All-Weather Artificial Turf field. Buildings 5000 and 8000 are excluded from this project's scope.

1545 Long Beach Blvd, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work:

This project includes the demolition of all existing buildings, shade structures and associated site work. In its place, a new softball field will be constructed to meet CIF field regulations, complete with fencing and gates. Above the softball field, a multi-purpose field will be built to soccer field specifications, including field goal posts. The project also includes the addition of a new backstop, bleachers, dugouts, lighting, scoreboard and fencing. Additionally, new restroom and storage structures will be incorporated into the site. The project further includes one 60-foot batting cages/bullpens combination for both the home and visitor teams, and bleachers to accommodate approximately 100 spectators. A  concessions and restroom building will also be constructed, along with an enclosed outdoor storage area. To complete the site, solid perimeter fencing and gates, sports field lighting and netting and a scoreboard will be added.

 

Poly Transformation

1600 Atlantic Ave, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work: The project involves modernizing Buildings 100, 200, 300, 400, 500, and 600, which includes HVAC installation, ADA upgrades, new projectors, marker boards, lighting, electrical upgrades, fire alarm upgrades, new signage, painting, and limited window refurbishment. Buildings 25 (Band) and 250 (Science) will undergo limited HVAC, electrical, low-voltage, and lighting upgrades.

Polytechnic High School | New Classroom Building [CTE] Q3 2025-2026

1600 Atlantic Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a three-story facility that will accommodate the MEDS program, Auto Shop program and Robotics program. In addition to these specialized programs, the building will feature general classrooms, special education classrooms and computer labs.

Polytechnic High School | Transformation Q3 2025-2026

1600 Atlantic Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project includes the demolition of buildings 150, 550, 700, 800, 850, and gym buildings 1000, 1100, and 1200, followed by the construction of five new buildings. Building 150 will be a one-story performing arts facility with drama and band classrooms. Building 700 will be a two-story student services building featuring a new lobby entrance, college and career center, wellness center and administrative offices. Building 800 will be a two-story gymnasium, with a large gym, small gym, wrestling and weight rooms, and locker rooms, all supporting the new pool. Building 850 will be a single-story pool equipment building, associated with a new pool, deck and spectator bleachers. Building 1000 will be a two-story classroom building. The site will also be reconstructed, including the reconfiguration of Jackrabbit Lane with an improved parking layout and new designated drop-off/pick-up lanes. Additional site upgrades include a new baseball field with sports lighting, new basketball courts, resurfacing of existing tennis courts and enhanced landscaping with fixed seating in courtyards and gardens.

Millikan High School | Aquatic Center Q3 2025-2026

Artist Renderings, Subject to Change

2800 Snowden Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a new aquatic center featuring two team locker rooms and an inclusive locker room. The new building will house an MPR classroom space, offices, a snack bar, and a ticket booth. The project also includes a new outdoor Myrtha pool, measuring 51.5 meters long by 25 yards wide, with a 1.5-meter wide bulkhead. Additionally, bleachers and shade covering will be installed for seating and comfort.

Millikan High School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q3 2025-2026

2800 Snowden Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project involves the installation of  HVAC in all permanent buildings, excluding the Gymnasium and the already air-conditioned Buildings 800 and 1100. It also includes comprehensive electrical upgrades across the campus, as well as the installation of a new fire alarm system. Accessibility improvements will feature the addition of three new elevators servicing Buildings 200, 300, 400 and 900. Additionally, classroom upgrades will align with the district's current standards, including the installation of new projectors, markerboards, ceilings, LED lighting, flooring and paint finishes.

Marshall Academy of the Arts | Heating, Ventilation and Air Conditioning (HVAC) Plus Q3 2025-2026

5870 E Wardlow Rd, Long Beach, CA 90808 

PROJECT OVERVIEW

Scope of Work: This project includes the installation of HVAC, utility infrastructure upgrades and improvements to accessibility, fire alarm and electrical systems.New projectors, projector screens, marker and tack boards, and AV systems will be installed. Accessibility improvements will be made throughout the campus, including the auditorium. Additionally, the project will feature landscape enhancements, new outdoor classrooms, and creative indoor learning spaces designed for collaboration.

Los Cerritos Elementary School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q3 2025-2026

515 W San Antonio Dr, Long Beach, CA 90807 

PROJECT OVERVIEW

Scope of Work: This project involves the comprehensive renovation of all existing buildings and portables. This includes the replacement of existing HVAC systems in all classrooms, offices and support spaces, such as the Auditorium, Cafeteria and Kitchen. Accessibility improvements will be made to the path of travel. The scope also includes new interior finishes, such as updated ceilings, flooring, paint and windows. Additionally, new LED lighting and an audiovisual system with overhead projectors will be installed. Campus-wide fire alarm upgrades are also part of the project. Outside, a new outdoor learning environment will be created, along with enhanced colored paving and a new turf play area.

1175 E 11th St, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work: This project includes upgrading the HVAC systems across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

PROJECT OVERVIEW

Scope of Work: This project includes updating the existing HVAC system across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

171 W Bort St, Long Beach, CA 90805 (Jordan Plus Campus) 

PROJECT OVERVIEW

Scope of Work: This project includes a new natural grass baseball field that will be installed at Jordan Plus for Jordan High School, including backstops, dugouts, batting cages, bullpens, scoreboard, concessions and ticketing areas, storage facilities, sports lighting, fencing, restroom facilities, and designated space for bleachers.

Jordan High School | Phase 6: Gymnasium and Pool Q3 2025-2026

6500 Atlantic Ave, Long Beach, CA 90805

PROJECT OVERVIEW

Scope of Work: This project will expand and enhance the school’s athletic facilities with the construction of new fields for softball, soccer, shot put, and discus, as well as new outdoor basketball courts. In addition, visitor bleachers will be installed to complement the newly constructed football stadium, providing an improved experience for spectators and the school community.

Jordan High School | Phase 5B: Sports Fields & Visitor Bleachers Q3 2025-2026

Artist Renderings, Subject to Change

6500 Atlantic Ave, Long Beach, CA 90805

PROJECT OVERVIEW

Scope of Work: This project will expand and enhance the school’s athletic facilities with the construction of new fields for softball, soccer, shot put, and discus, as well as new outdoor basketball courts. In addition, visitor bleachers will be installed to complement the newly constructed football stadium, providing an improved experience for spectators and the school community.

Hoover Middle School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q3 2025-2026

PROJECT OVERVIEW


Scope of Work: This project includes the installation of HVAC across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

3720 Canehill Ave, Long Beach, CA 90808

PROJECT OVERVIEW

Scope of Work: This project includes the installation of HVAC across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

Carver Elementary School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q3 2025-2026

 

PROJECT OVERVIEW


Scope of Work: This project includes the installation of HVAC, utility infrastructure upgrades and necessary accessibility and hardware improvements. It also covers ceiling and LED lighting replacements, fire alarm and electrical system upgrades, and door replacements. Additional work will involve building finish upgrades, new tactile signage, projectors, projection screens, marker and tack boards, as well as an expanded kindergarten playground and a new natural grass playfield.

Addams Elementary School  | Modernization Plus Q3 2025-2026

Artist Renderings, Subject to Change

PROJECT OVERVIEW
Scope of Work: This project entails the renovation of all campus buildings, including portables, with new HVAC systems in classrooms, offices, and key areas such as the Auditorium, Cafeteria, and Kitchen. It includes accessibility upgrades, necessary utility improvements, and the replacement of building finishes like ceilings, flooring, painting, and lighting. New tactile signage will be added campus-wide, along with fire alarm system upgrades and seismic enhancements where required by DSA standards.

Washington Middle School | Transformation Q2 2025-2026

1450 Cedar Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project involves demolishing the entire middle school campus and constructing a completely new facility. The new campus will feature an auditorium, classrooms, a gymnasium, science labs, a state-of-the-art engineering building, new basketball courts, the first underground parking structure and a new turf soccer field.

Stevenson Elementary School | Modernization Plus Q2 2025-2026

Artist Renderings, Subject to Change

515 Lime Ave, Long Beach, CA 90802 

PROJECT OVERVIEW

Scope of Work: This project includes the replacement of existing HVAC system, which dates back to the 1990s, with a new, energy-efficient system. Accessibility will be improved with the installation of a new elevator, providing access to both two-story buildings in compliance with current accessibility standards. Additionally, classrooms will be renovated to meet current FDS standards, incorporating new projectors, markerboards, ceilings, lighting, paint and floor finishes to enhance the learning environment.

Sato Academy of Mathematics & Science | Heating, Ventilation and Air Conditioning (HVAC) Plus Q2 2025-2026

1100 Iroquois Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project includes significant mechanical, utility, and facility upgrades. Key improvements involve the installation of HVAC, upgrades to the utility infrastructure, and replacement of the fire alarm and electrical systems. Accessibility will be enhanced campus-wide, with specific focus on improvements within the auditorium, cafeteria, and kitchen. The project also covers the installation of new interior teaching and presentation tools, including projectors, screens, marker/tack boards, and AV systems. Finally, the existing natural turf field will be converted to a new All-Weather Artificial Turf field. Buildings 5000 and 8000 are excluded from this project's scope.

Poly Transformation

1600 Atlantic Ave, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work: The project involves modernizing Buildings 100, 200, 300, 400, 500, and 600, which includes HVAC installation, ADA upgrades, new projectors, marker boards, lighting, electrical upgrades, fire alarm upgrades, new signage, painting, and limited window refurbishment. Buildings 25 (Band) and 250 (Science) will undergo limited HVAC, electrical, low-voltage, and lighting upgrades.

Polytechnic High School | Transformation Q2 2025-2026

1600 Atlantic Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project includes the demolition of buildings 150, 550, 700, 800, 850, and gym buildings 1000, 1100, and 1200, followed by the construction of five new buildings. Building 150 will be a one-story performing arts facility with drama and band classrooms. Building 700 will be a two-story student services building featuring a new lobby entrance, college and career center, wellness center and administrative offices. Building 800 will be a two-story gymnasium, with a large gym, small gym, wrestling and weight rooms, and locker rooms, all supporting the new pool. Building 850 will be a single-story pool equipment building, associated with a new pool, deck and spectator bleachers. Building 1000 will be a two-story classroom building. The site will also be reconstructed, including the reconfiguration of Jackrabbit Lane with an improved parking layout and new designated drop-off/pick-up lanes. Additional site upgrades include a new baseball field with sports lighting, new basketball courts, resurfacing of existing tennis courts and enhanced landscaping with fixed seating in courtyards and gardens.

Polytechnic High School | New Classroom Building [CTE] Q2 2025-2026

1600 Atlantic Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a three-story facility that will accommodate the MEDS program, Auto Shop program and Robotics program. In addition to these specialized programs, the building will feature general classrooms, special education classrooms and computer labs.

Millikan High School | Aquatic Center Q2 2025-2026

Artist Renderings, Subject to Change

2800 Snowden Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a new aquatic center featuring two team locker rooms and an inclusive locker room. The new building will house an MPR classroom space, offices, a snack bar, and a ticket booth. The project also includes a new outdoor Myrtha pool, measuring 51.5 meters long by 25 yards wide, with a 1.5-meter wide bulkhead. Additionally, bleachers and shade covering will be installed for seating and comfort.

Millikan High School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q2 2025-2026

2800 Snowden Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project involves the installation of  HVAC in all permanent buildings, excluding the Gymnasium and the already air-conditioned Buildings 800 and 1100. It also includes comprehensive electrical upgrades across the campus, as well as the installation of a new fire alarm system. Accessibility improvements will feature the addition of three new elevators servicing Buildings 200, 300, 400 and 900. Additionally, classroom upgrades will align with the district's current standards, including the installation of new projectors, markerboards, ceilings, LED lighting, flooring and paint finishes.

Marshall Academy of the Arts | Heating, Ventilation and Air Conditioning (HVAC) Plus Q2 2025-2026

5870 E Wardlow Rd, Long Beach, CA 90808 

PROJECT OVERVIEW

Scope of Work: This project includes the installation of HVAC, utility infrastructure upgrades and improvements to accessibility, fire alarm and electrical systems.New projectors, projector screens, marker and tack boards, and AV systems will be installed. Accessibility improvements will be made throughout the campus, including the auditorium. Additionally, the project will feature landscape enhancements, new outdoor classrooms, and creative indoor learning spaces designed for collaboration.

Los Cerritos Elementary School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q2 2025-2026

515 W San Antonio Dr, Long Beach, CA 90807 

PROJECT OVERVIEW

Scope of Work: This project involves the comprehensive renovation of all existing buildings and portables. This includes the replacement of existing HVAC systems in all classrooms, offices and support spaces, such as the Auditorium, Cafeteria and Kitchen. Accessibility improvements will be made to the path of travel. The scope also includes new interior finishes, such as updated ceilings, flooring, paint and windows. Additionally, new LED lighting and an audiovisual system with overhead projectors will be installed. Campus-wide fire alarm upgrades are also part of the project. Outside, a new outdoor learning environment will be created, along with enhanced colored paving and a new turf play area.

1175 E 11th St, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work: This project includes upgrading the HVAC systems across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

PROJECT OVERVIEW

Scope of Work: This project includes updating the existing HVAC system across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

Jordan High School | Phase 6: Gymnasium and Pool Q2 2025-2026

6500 Atlantic Ave, Long Beach, CA 90805

PROJECT OVERVIEW

Scope of Work: This project will expand and enhance the school’s athletic facilities with the construction of new fields for softball, soccer, shot put, and discus, as well as new outdoor basketball courts. In addition, visitor bleachers will be installed to complement the newly constructed football stadium, providing an improved experience for spectators and the school community.

Jordan High School | Phase 5B: Sports Fields & Visitor Bleachers Q2 2025-2026

Artist Renderings, Subject to Change

6500 Atlantic Ave, Long Beach, CA 90805

PROJECT OVERVIEW

Scope of Work: This project will expand and enhance the school’s athletic facilities with the construction of new fields for softball, soccer, shot put, and discus, as well as new outdoor basketball courts. In addition, visitor bleachers will be installed to complement the newly constructed football stadium, providing an improved experience for spectators and the school community.

Hoover Middle School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q2 2025-2026

PROJECT OVERVIEW


Scope of Work: This project includes the installation of HVAC across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

3720 Canehill Ave, Long Beach, CA 90808

PROJECT OVERVIEW

Scope of Work: This project includes the installation of HVAC across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

Carver Elementary School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q2 2025-2026

 

PROJECT OVERVIEW


Scope of Work: This project includes the installation of HVAC, utility infrastructure upgrades and necessary accessibility and hardware improvements. It also covers ceiling and LED lighting replacements, fire alarm and electrical system upgrades, and door replacements. Additional work will involve building finish upgrades, new tactile signage, projectors, projection screens, marker and tack boards, as well as an expanded kindergarten playground and a new natural grass playfield.

Addams Elementary School  | Modernization Plus Q2 2025-2026

Artist Renderings, Subject to Change

PROJECT OVERVIEW
Scope of Work: This project entails the renovation of all campus buildings, including portables, with new HVAC systems in classrooms, offices, and key areas such as the Auditorium, Cafeteria, and Kitchen. It includes accessibility upgrades, necessary utility improvements, and the replacement of building finishes like ceilings, flooring, painting, and lighting. New tactile signage will be added campus-wide, along with fire alarm system upgrades and seismic enhancements where required by DSA standards.

Wilson High School | Aquatic Center Q1 2025-2026 [Construction Completed]

September 2025

PROJECT OVERVIEW

The Long Beach Unified School District completed the Wilson High School Aquatic Center. The project delivered a modern, multi-functional facility centered around a state-of-the-art inground Myrtha pool. The construction involved three new support buildings designed to significantly upgrade athletic programs and enhance the spectator experience by housing essential facilities, modern locker rooms, staff offices, and critical operational spaces.

Washington Middle School | Transformation Q1 2025-2026

1450 Cedar Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project involves demolishing the entire middle school campus and constructing a completely new facility. The new campus will feature an auditorium, classrooms, a gymnasium, science labs, a state-of-the-art engineering building, new basketball courts, the first underground parking structure and a new turf soccer field.

Tincher Preparatory School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q1 2025-2026

1701 Petaluma Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project involves the installation of a new HVAC system and upgrades to utility infrastructure. It also includes the creation of new outdoor learning spaces, along with essential accessibility improvements and updates to doors and hardware. The scope of work further includes the replacement of ceilings and LED lighting, the installation of a new fire alarm system and upgrades to the electrical system. Additional enhancements include building finish upgrades, the installation of new tactile signage, new audio-visual systems and the addition of new marker and tack boards.

Stevenson Elementary School | Modernization Plus Q1 2025-2026

Artist Renderings, Subject to Change

515 Lime Ave, Long Beach, CA 90802 

PROJECT OVERVIEW

Scope of Work: This project includes the replacement of existing HVAC system, which dates back to the 1990s, with a new, energy-efficient system. Accessibility will be improved with the installation of a new elevator, providing access to both two-story buildings in compliance with current accessibility standards. Additionally, classrooms will be renovated to meet current FDS standards, incorporating new projectors, markerboards, ceilings, lighting, paint and floor finishes to enhance the learning environment.

Stanford Middle School | Heating, Ventilation and Air Conditioning (HVAC) Q1 2025-2026 [Construction Completed]

5871 E Los Arcos St, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project involves the installation of HVAC, utility infrastructure upgrades, and necessary accessibility improvements, including door and hardware enhancements. It also features ceiling and LED lighting replacements, installation of a new fire alarm system and upgrades to the electrical system. Additional work includes building finish upgrades, the installation of new tactile signage, new audio-visual systems and the addition of new marker and tack boards.

Sato Academy of Mathematics & Science | Heating, Ventilation and Air Conditioning (HVAC) Plus Q1 2025-2026

1100 Iroquois Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project includes significant mechanical, utility, and facility upgrades. Key improvements involve the installation of HVAC, upgrades to the utility infrastructure, and replacement of the fire alarm and electrical systems. Accessibility will be enhanced campus-wide, with specific focus on improvements within the auditorium, cafeteria, and kitchen. The project also covers the installation of new interior teaching and presentation tools, including projectors, screens, marker/tack boards, and AV systems. Finally, the existing natural turf field will be converted to a new All-Weather Artificial Turf field. Buildings 5000 and 8000 are excluded from this project's scope.

1600 Atlantic Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project includes the demolition of buildings 150, 550, 700, 800, 850, and gym buildings 1000, 1100, and 1200, followed by the construction of five new buildings. Building 150 will be a one-story performing arts facility with drama and band classrooms. Building 700 will be a two-story student services building featuring a new lobby entrance, college and career center, wellness center and administrative offices. Building 800 will be a two-story gymnasium, with a large gym, small gym, wrestling and weight rooms, and locker rooms, all supporting the new pool. Building 850 will be a single-story pool equipment building, associated with a new pool, deck and spectator bleachers. Building 1000 will be a two-story classroom building. The site will also be reconstructed, including the reconfiguration of Jackrabbit Lane with an improved parking layout and new designated drop-off/pick-up lanes. Additional site upgrades include a new baseball field with sports lighting, new basketball courts, resurfacing of existing tennis courts and enhanced landscaping with fixed seating in courtyards and gardens.

Polytechnic High School | Field Improvements [Softball] Q1 2025-2026

Artist Renderings, Subject to Change

1600 Atlantic Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project includes the demolition of all existing buildings, shade structures and associated site work. In its place, a new softball field will be constructed to meet CIF field regulations, complete with fencing and gates. Above the softball field, a multi-purpose field will be built to soccer field specifications, including field goal posts. The project also includes the addition of a new backstop, bleachers, dugouts, lighting, scoreboard and fencing. Additionally, new restroom and storage structures will be incorporated into the site. The project further includes one 60-foot batting cages/bullpens cmbination for both the home and visitor teams, and bleachers to accommodate approximately 100 spectators. A  concessions and restroom building will also be constructed, along with an enclosed outdoor storage area. To complete the site, solid perimeter fencing and gates, sports field lighting and netting and a scoreboard will be added.**

Polytechnic High School | Heating, Ventilation and Air Conditioning (HVAC) Q1 2025-2026

1600 Atlantic Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: The project involves modernizing Buildings 100, 200, 300, 400, 500, and 600, which includes HVAC installation, ADA upgrades, new projectors, marker boards, lighting, electrical upgrades, fire alarm upgrades, new signage, painting, and limited window refurbishment. Buildings 25 (Band) and 250 (Science) will undergo limited HVAC, electrical, low-voltage, and lighting upgrades.

Polytechnic High School | New Classroom Building [CTE] Q1 2025-2026

1600 Atlantic Ave, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a three-story facility that will accommodate the MEDS program, Auto Shop program and Robotics program. In addition to these specialized programs, the building will feature general classrooms, special education classrooms and computer labs.

Millikan High School | Aquatic Center Q1 2025-2026

Artist Renderings, Subject to Change

2800 Snowden Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a new aquatic center featuring two team locker rooms and an inclusive locker room. The new building will house an MPR classroom space, offices, a snack bar, and a ticket booth. The project also includes a new outdoor Myrtha pool, measuring 51.5 meters long by 25 yards wide, with a 1.5-meter wide bulkhead. Additionally, bleachers and shade covering will be installed for seating and comfort.

Millikan High School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q1 2025-2026

2800 Snowden Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project involves the installation of  HVAC in all permanent buildings, excluding the Gymnasium and the already air-conditioned Buildings 800 and 1100. It also includes comprehensive electrical upgrades across the campus, as well as the installation of a new fire alarm system. Accessibility improvements will feature the addition of three new elevators servicing Buildings 200, 300, 400 and 900. Additionally, classroom upgrades will align with the district's current standards, including the installation of new projectors, markerboards, ceilings, LED lighting, flooring and paint finishes.

Marshall Academy of the Arts | Heating, Ventilation and Air Conditioning (HVAC) Plus Q1 2025-2026

5870 E Wardlow Rd, Long Beach, CA 90808 

PROJECT OVERVIEW

Scope of Work: This project includes the installation of HVAC, utility infrastructure upgrades and improvements to accessibility, fire alarm and electrical systems.New projectors, projector screens, marker and tack boards, and AV systems will be installed. Accessibility improvements will be made throughout the campus, including the auditorium. Additionally, the project will feature landscape enhancements, new outdoor classrooms, and creative indoor learning spaces designed for collaboration.

Los Cerritos Elementary School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q1 2025-2026

515 W San Antonio Dr, Long Beach, CA 90807 

PROJECT OVERVIEW

Scope of Work: This project involves the comprehensive renovation of all existing buildings and portables. This includes the replacement of existing HVAC systems in all classrooms, offices and support spaces, such as the Auditorium, Cafeteria and Kitchen. Accessibility improvements will be made to the path of travel. The scope also includes new interior finishes, such as updated ceilings, flooring, paint and windows. Additionally, new LED lighting and an audiovisual system with overhead projectors will be installed. Campus-wide fire alarm upgrades are also part of the project. Outside, a new outdoor learning environment will be created, along with enhanced colored paving and a new turf play area.

Lincoln Elementary School | Modernization Plus Q1 2025-2026

1175 E 11th St, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work: This project includes upgrading the HVAC systems across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

Lakewood High School | Aquatic Center Q1 2025-2026 [Construction Completed]

PROJECT OVERVIEW

The The Long Beach Unified School District completed the Lakewood Aquatic Center. The project delivered a state-of-the-art competitive swimming facility designed to serve the community and support high-level aquatic events. The comprehensive construction involved relocating the existing softball field to accommodate the new complex, which includes a new, flexible competition pool and modern support infrastructure, significantly enhancing the area's recreational and athletic capabilities.

Jordan High School | Phase 6: Gymnasium and Pool Q1 2025-2026

6500 Atlantic Ave, Long Beach, CA 90805

PROJECT OVERVIEW

Scope of Work: This project will expand and enhance the school’s athletic facilities with the construction of new fields for softball, soccer, shot put, and discus, as well as new outdoor basketball courts. In addition, visitor bleachers will be installed to complement the newly constructed football stadium, providing an improved experience for spectators and the school community.

Jordan High School | Phase 5B: Sports Fields & Visitor Bleachers Q1 2025-2026

Artist Renderings, Subject to Change

6500 Atlantic Ave, Long Beach, CA 90805

PROJECT OVERVIEW

Scope of Work: This project will expand and enhance the school’s athletic facilities with the construction of new fields for softball, soccer, shot put, and discus, as well as new outdoor basketball courts. In addition, visitor bleachers will be installed to complement the newly constructed football stadium, providing an improved experience for spectators and the school community.

Jordan High School | Phase 5A: Stadium Modernization (Bleachers & Athletic Fields) Q1 2025-2026 [Construction Completed]

PROJECT OVERVIEW

The Long Beach Unified School District completed a comprehensive modernization of the Jordan High School athletics stadium, delivering a state-of-the-art facility designed to support student-athletes and enhance the fan experience. The project replaced outdated infrastructure and added new amenities to serve their football and soccer programs.

Hoover Middle School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q1 2025-2026

PROJECT OVERVIEW


Scope of Work: This project includes the installation of HVAC across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

Henry Elementary School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q1 2025-2026

3720 Canehill Ave, Long Beach, CA 90808

PROJECT OVERVIEW

Scope of Work: This project includes the installation of HVAC across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

Hamilton Middle School | New Gymnasium Q1 2025-2026

1060 70th St, Long Beach, CA 90805

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a new gymnasium building with locker rooms and the demolition of the existing gymnasium. New playcourts will be installed in the newly paved area. Accessibility upgrades will be implemented across the campus. Alterations will be made to two existing SDC classrooms in building 500. A full campus electrical upgrade will be completed, along with the relocation of four classroom portables and one restroom portable.

Gompers Elementary School | Heating, Ventilation and Air Conditioning (HVAC) Q1 2025-2026 [Construction Completed]

PROJECT OVERVIEW

The Long Beach Unified School District completed a comprehensive facility modernization project at Gompers Elementary School, focused on enhancing safety, efficiency, and the learning environment. This extensive scope included the installation of a new HVAC system and an upgrade to the utility infrastructure to improve overall building performance and sustainability.

Gant Elementary School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q1 2025-2026

1854 N Britton Dr, Long Beach, CA 90815

PROJECT OVERVIEW

Scope of Work: This project includes the installation of a new HVAC system, utility infrastructure upgrades and a redesigned student drop-off area. It also involves the addition of a new lunch shelter and outdoor learning spaces, along with essential accessibility improvements and updates to doors and hardware. The scope of work further includes ceiling and LED lighting replacements, installation of a new fire alarm system and upgrades to the electrical system. Additional improvements involve building finish upgrades, the installation of new tactile signage, new audio-visual systems and the addition of new marker and tack boards.

Carver Elementary School | Heating, Ventilation and Air Conditioning (HVAC) Plus Q1 2025-2026

5335 E Pavo St, Long Beach, CA 90808

PROJECT OVERVIEW

Scope of Work: This project includes the installation of a new HVAC system, utility infrastructure upgrades and necessary accessibility and hardware improvements. It also covers ceiling and LED lighting replacements, fire alarm and electrical system upgrades, and door replacements. Additional work will involve building finish upgrades, new tactile signage, projectors, projection screens, marker and tack boards, as well as an expanded kindergarten playground and a new natural grass playfield.

Avalon K-12 School  | Site Improvements: Baseball Field Q1 2025-2026

200 Falls Canyon Rd, Avalon, CA 9070

PROJECT OVERVIEW

Scope of Work: This project includes the installation of a new artificial turf field, a new scoreboard and accessibility upgrades, including improved parking facilities. Additionally, a baseball field will be constructed, along with an 8x8 football/soccer field.

Addams Elementary School  | Modernization Plus Q1 2025-2026

Artist Renderings, Subject to Change

5320 Pine Ave, Long Beach, CA 90805

PROJECT OVERVIEW

Scope of Work: This project entails the renovation of all campus buildings, including portables, with replacement HVAC systems in classrooms, offices, and key areas such as the Auditorium, Cafeteria, and Kitchen. It includes accessibility upgrades, necessary utility improvements, and the replacement of building finishes like ceilings, flooring, painting, and lighting. New tactile signage will be added campus-wide, along with fire alarm system upgrades and seismic enhancements where required by DSA standards.

Washington Middle School | Transformation Q2 2024-2025


1450 Cedar Ave., Long Beach CA 90813

PROJECT OVERVIEW

Scope of Work: This project involves demolishing the entire middle school campus and constructing a completely new facility. The new campus will feature an auditorium, classrooms, a gymnasium, science labs, a state-of-the-art engineering building, new basketball courts, the first underground parking structure and a new turf soccer field.

Wilson High School | Aquatic Center Q2 2024-2025

4400 E 10th St., Long Beach, CA 90804 

PROJECT OVERVIEW


Scope of Work: This project includes the construction of three new buildings, designed to support a variety of functions. These buildings will house the girls' and boys' locker rooms, staff offices, restrooms, modern locker rooms and gender-neutral restrooms. Additional spaces will include multi-purpose rooms, as well as mechanical and electrical rooms, concessions, storage areas and ticket booths. A key feature of the project is the construction of a state-of-the-art underground Myrtha pool.

Tincher HVAC

1701 Petaluma Ave, Long Beach, CA 90815

PROJECT OVERVIEW

Scope of Work: This project involves the installation of a new HVAC system and upgrades to utility infrastructure. It also includes the creation of new outdoor learning spaces, along with essential accessibility improvements and updates to doors and hardware. The scope of work further includes the replacement of ceilings and LED lighting, the installation of a new fire alarm system and upgrades to the electrical system. Additional enhancements include building finish upgrades, the installation of new tactile signage, new audio-visual systems and the addition of new marker and tack boards.

Stevenson Elementary School  | Modernization Plus Q2 2024-2025

515 Lime Ave, Long Beach, CA 90802 

PROJECT OVERVIEW

Scope of Work: This project includes upgrading the existing HVAC system, which dates back to the 1990s, with a new, energy-efficient system. Accessibility will be improved with the installation of a new elevator, providing access to both two-story buildings in compliance with current accessibility standards. Additionally, classrooms will be renovated to meet current FDS standards, incorporating new projectors, markerboards, ceilings, lighting, paint and floor finishes to enhance the learning environment.

Stanford HVAC

5871 E Los Arcos St, Long Beach, CA 90815

PROJECT OVERVIEW

Scope of Work: This project involves the installation of a new HVAC system, utility infrastructure upgrades, and necessary accessibility improvements, including door and hardware enhancements. It also features ceiling and LED lighting replacements, installation of a new fire alarm system and upgrades to the electrical system. Additional work includes building finish upgrades, the installation of new tactile signage, new audio-visual systems and the addition of new marker and tack boards.

Poly Transformation

Artist Renderings, Subject to Change

1600 Atlantic Ave, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work: This project includes the demolition of buildings 150, 550, 700, 800, 850, and gym buildings 1000, 1100, and 1200, followed by the construction of five new buildings. Building 150 will be a one-story performing arts facility with drama and band classrooms. Building 700 will be a two-story student services building featuring a new lobby entrance, college and career center, wellness center and administrative offices. Building 800 will be a two-story gymnasium, with a large gym, small gym, wrestling and weight rooms, and locker rooms, all supporting the new pool. Building 850 will be a single-story pool equipment building, associated with a new pool, deck and spectator bleachers. Building 1000 will be a two-story classroom building. The site will also be reconstructed, including the reconfiguration of Jackrabbit Lane with an improved parking layout and new designated drop-off/pick-up lanes. Additional site upgrades include a new baseball field with sports lighting, new basketball courts, resurfacing of existing tennis courts and enhanced landscaping with fixed seating in courtyards and gardens.

Poly Transformation

1600 Atlantic Ave, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work: This project includes the demolition of all existing buildings, shade structures and associated site work. In its place, a new softball field will be constructed to meet CIF field regulations, complete with fencing and gates. Above the softball field, a multi-purpose field will be built to CIF soccer field specifications, including field goal posts. The project also includes the addition of a new backstop, bleachers, dugouts, lighting, scoreboard and fencing. Additionally, new restroom and storage structures will be incorporated into the site. The project further includes two 60-foot batting cages, bullpens for both the home and visitor teams, and elevated bleachers with a ramp and stairs to accommodate 200 spectators. A ticketing, concessions and restroom building will also be constructed, along with an enclosed outdoor storage area. To complete the site, chain link perimeter fencing and gates, sports field lighting and a scoreboard will be added.

Poly Transformation

Artist Renderings, Subject to Change

1600 Atlantic Ave, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a three-story facility that will accommodate the MEDS program, Auto Shop program and Robotics program. In addition to these specialized programs, the building will feature general classrooms, special education classrooms and computer labs.

Poly Transformation

1600 Atlantic Ave, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work: The project involves modernizing Buildings 100, 200, 300, 400, 500, and 600, which includes HVAC installation, ADA upgrades, new projectors, marker boards, lighting, electrical upgrades, fire alarm upgrades, new signage, painting, and limited window refurbishment. Buildings 25 (Band) and 250 (Science) will undergo limited HVAC, electrical, low-voltage, and lighting upgrades.

Poly Transformation

1600 Atlantic Ave, Long Beach, CA 90813

PROJECT OVERVIEW

Scope of Work: The project includes the addition of relocatable buildings, shade structures, restroom facilities and the necessary utility connections to support these new structures.

Millikan Transformation

Artist Renderings, Subject to Change.

2800 Snowden Ave, Long Beach, CA 90815

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a new aquatic center featuring two team locker rooms and an inclusive locker room. The new building will house an MPR classroom space, offices, a snack bar, and a ticket booth. The project also includes a new outdoor Myrtha pool, measuring 51.5 meters long by 25 yards wide, with a 1.5-meter wide bulkhead. Additionally, bleachers and shade covering will be installed for seating and comfort.

Millikan Transformation

2800 Snowden Ave, Long Beach, CA 90815 

PROJECT OVERVIEW

Scope of Work: This project involves the installation of a new HVAC system in all permanent buildings, excluding the Gymnasium and the already air-conditioned Buildings 800 and 1100. It also includes comprehensive electrical upgrades across the campus, as well as the installation of a new fire alarm system. Accessibility improvements will feature the addition of three new elevators servicing Buildings 200, 300, 400 and 900. Additionally, classroom upgrades will align with the district's current standards, including the installation of new projectors, markerboards, ceilings, LED lighting, flooring and paint finishes.

Marshall Transformation

Artist Renderings, Subject to Change.

5870 E Wardlow Rd, Long Beach, CA 90808 

PROJECT OVERVIEW

Scope of Work: This project includes the installation of a new HVAC system, utility infrastructure upgrades and improvements to accessibility, fire alarm and electrical systems.New projectors, projector screens, marker and tack boards, and AV systems will be installed. Accessibility improvements will be made throughout the campus, including the auditorium. Additionally, the project will feature landscape enhancements, new outdoor classrooms, and creative indoor learning spaces designed for collaboration.

Los Cerritos Transformation

Artist Renderings, Subject to Change.

515 W San Antonio Dr, Long Beach, CA 90807 

PROJECT OVERVIEW

Scope of Work: This project involves the comprehensive renovation of all existing buildings and portables. This includes the installation of HVAC systems in all classrooms, offices and support spaces, such as the Auditorium, Cafeteria and Kitchen. Accessibility improvements will be made to the path of travel. The scope also includes new interior finishes, such as updated ceilings, flooring, paint and windows. Additionally, new LED lighting and an audiovisual system with overhead projectors will be installed. Campus-wide fire alarm upgrades are also part of the project. Outside, a new outdoor learning environment will be created, along with enhanced colored paving and a new turf play area.

Lincoln Elementary School | Modernization Plus Q2 2024-2025

1175 E 11th St, Long Beach, CA 90813 

PROJECT OVERVIEW

Scope of Work: This project includes the installation of HVAC across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response

Lakewood Transformation

4400 Briercrest Ave, Lakewood, CA 90713

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a 51.5-meter by 25-yard modular swimming pool, featuring a concrete pool floor, stairs and a prefabricated Myrtha panel pool with a bulkhead system. It also involves the construction of a new locker room support building, ticketing/snack bar building and mechanical equipment building for the pool facility. Additional elements include spectator seating with a canopy, outdoor deck storage areas, event lighting and a digital event scoreboard.

Jordan Transformation

6500 Atlantic Ave, Long Beach, CA 90805

PROJECT OVERVIEW

Scope of Work: This project includes the construction of a new gymnasium building, as well as a new outdoor competition swimming pool with bleachers and a ticket/concessions area. The existing indoor pool will be converted into an auxiliary gym to provide additional space for activities.

Jordan Transformation

 6500 Atlantic Ave, Long Beach, CA 90805 

PROJECT OVERVIEW

Scope of Work: The project includes the replacement of the bleachers for both home and visitor seating, as well as the restrooms and ticket/concessions areas. The existing fields will be replaced with a new all-weather track and field to accommodate football and soccer. Additionally, new athletic fields for baseball and softball will be constructed, along with new basketball courts, enhancing the campus’s sports facilities.

Hoover Transformation

3501 Country Club Dr, Lakewood, CA 90712 

PROJECT OVERVIEW

Scope of Work: This project includes the installation of HVAC across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

Henry Transformation

3720 Canehill Ave, Long Beach, CA 90808

PROJECT OVERVIEW

Scope of Work: This project includes the installation of HVAC across the campus for improved climate control, accessibility upgrades to enhance inclusivity and meet modern standards, and classroom technology upgrades with new projectors and markerboards. Interior improvements will involve new ceilings and lighting, while the fire alarm system will be upgraded campus-wide to enhance safety and response.

Gant Transformation

1854 N Britton Dr, Long Beach, CA 90815

PROJECT OVERVIEW

Scope of Work: This project includes the installation of a new HVAC system, utility infrastructure upgrades and a redesigned student drop-off area. It also involves the addition of a new lunch shelter and outdoor learning spaces, along with essential accessibility improvements and updates to doors and hardware. The scope of work further includes ceiling and LED lighting replacements, installation of a new fire alarm system and upgrades to the electrical system. Additional improvements involve building finish upgrades, the installation of new tactile signage, new audio-visual systems and the addition of new marker and tack boards.

Carver Transformation

Artist Renderings, Subject to Change.

5335 E Pavo St, Long Beach, CA 90808

PROJECT OVERVIEW

Scope of Work: This project includes the installation of a new HVAC system, utility infrastructure upgrades and necessary accessibility and hardware improvements. It also covers ceiling and LED lighting replacements, fire alarm and electrical system upgrades, and door replacements. Additional work will involve building finish upgrades, new tactile signage, projectors, projection screens, marker and tack boards, as well as an expanded kindergarten playground and a new natural grass playfield.

Avalon Transformation

 200 Falls Canyon Rd, Avalon, CA 90704

PROJECT OVERVIEW

Scope of Work: This project includes the installation of a new artificial turf field, a new scoreboard and accessibility upgrades, including improved parking facilities. Additionally, a baseball field will be constructed, along with an 8x8 football/soccer field.

Avalon Transformation

200 Falls Canyon Rd, Avalon, CA 90704

PROJECT OVERVIEW

Scope of Work: This project included the installation of new HVAC systems in all permanent buildings, along with an upgrade to the utility infrastructure, which covers fire alarm systems and audiovisual (AV) equipment. Classrooms will be renovated to meet district standards, with improvements such as new projectors, markerboards, windows and fresh interior painting and finishes. Additionally, new security fencing will be installed around the site's perimeter to enhance safety and protection.

Addams Transformation

Artist Renderings, Subject to Change.

5320 Pine Ave, Long Beach, CA 90805

PROJECT OVERVIEW

Scope of Work: This project entails the renovation of all campus buildings, including portables, with new HVAC systems in classrooms, offices, and key areas such as the Auditorium, Cafeteria, and Kitchen. It includes accessibility upgrades, necessary utility improvements, and the replacement of building finishes like ceilings, flooring, painting, and lighting. New tactile signage will be added campus-wide, along with fire alarm system upgrades and seismic enhancements where required by DSA standards.