Bond Funds At Work
Welcome to our District Bond Project page, where you can find information on the exciting renovations and construction activities happening across Long Beach Unified School District. We’re committed to enhancing our schools with state-of-the-art facilities that support student learning and community growth. Check back regularly for the latest updates and feel free to reach out if you have any questions about our ongoing projects.
Early Learning
Elementary Schools
In Progress

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: June 2025
Projected Completion: April 2027
Supported by Bond Measure: E
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: June 2025
Projected Completion: August 2026
Supported by Bond Measure: E
Learn More
Upcoming

Project Type: Campuswide Renovation
Construction Begins: June 2027
Projected Completion: August 2028
Supported by Bond Measure: E

Project Type: Campuswide Renovation
Construction Begins: June 2029
Projected Completion: August 2030
Supported by Bond Measure: Q
Learn More

Project Type: Campuswide Renovation
Construction Begins: June 2028
Projected Completion: August 2030
Supported by Bond Measure: Q
Learn More

Project Type: Campuswide Renovation
Construction Begins: June 2029
Projected Completion: August 2030
Supported by Bond Measure: Q

Project Type: Campuswide Renovation
Construction Begins: June 2028
Projected Completion: August 2029
Supported by Bond Measure: Q
Learn More

Project Type: Heating Ventilation & Air Conditioning
Construction Begins: June 2026
Projected Completion: August 2027
Supported by Bond Measure: E
Learn More

Project Type: Campuswide Renovation
Construction Begins: June 2026
Projected Completion: August 2027
Supported by Bond Measure: Q
Learn More

Project Type: Campuswide Renovation
Construction Begins: June 2027
Projected Completion: August 2029
Supported by Bond Measure: Q
Learn More

Project Type: Campuswide Renovation
Construction Begins: June 2027
Projected Completion: August 2028
Supported by Bond Measure: Q
Learn More
Recently Completed

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: April 2023
Project Completed: August 2024
Supported by Bond Measure: E
Learn More

Project Type: Solar Canopy Installation
Construction Began: February 2026
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: Solar Canopy Installation
Construction Began: Nov. 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: Solar Canopy Installation
Construction Began: July 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: Solar Canopy Installation
Construction Began: August 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: August 2023
Project Completed: June 2025
Supported by Bond Measure: E
Learn More

Project Type: Solar Canopy Installation
Construction Began: July 2025
Projected Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: Solar Canopy Installation
Construction Began: Dec. 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: Solar Canopy Installation
Construction Began: August 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: April 2022
Project Completed: September 2024
Supported by Bond Measure: E
Learn More

Project Type: Solar Canopy Installation
Construction Began: November 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: June 2024
Project Completed: Nov. 2025
Supported by Bond Measure: E
Learn More

Project Type: Solar Canopy Installation
Construction Began: July 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: Solar Canopy Installation
Construction Began: January 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More
School Specific Projects
- Jane Addams Elementary School
- Alvarado Elementary School
- Barton Elementary School
- Beach K-5
- Birney Elementary School
- Bixby Elementary School
- Bryant Elementary School
- Burbank Elementary School
- David Burcham Elementary School
- Carver Elementary School
- Cesar Chavez Elementary School
- Cleveland Elementary School
- Dooley Elementary School
- Edison Elementary School
- Emerson Parkside Academy
- Fremont Elementary School
- Minnie Gant Elementary School
- Garfield Elementary School
- Gompers Elementary School
- Grant Elementary School
- Bret Harte Elementary School
- Patrick Henry Elementary School
- Holmes Elementary School
- Kettering Elementary School
- Starr King Elementary School
- Lafayette Elementary School
- Lincoln Elementary School
- Longfellow Elementary School
- Los Cerritos Elementary School
- Lowell Elementary School
- MacArthur Elementary School
- Madison Elementary School
- Mann Elementary School
- McKinley Elementary School
- Monroe Elementary School
- Muir Academy
- Naples Bayside Academy
- Newcomb K-8 Academy
- Nieto Herrera Elementary School
- Oropeza Elementary School
- Powell Academy for Success
- Prisk Elementary School
- Riley Elementary School
- Roosevelt Elementary School
- Signal Hill Elementary School
- Smith Elementary School
- Stevenson Elementary School
- Tincher Preparatory School
- Mark Twain Elementary School
- Webster Elementary School
- Whittier Elementary School
- Willard Elementary School
Jane Addams Elementary School
Alvarado Elementary School
Barton Elementary School
Beach K-5
Birney Elementary School
Bixby Elementary School
Bryant Elementary School
Burbank Elementary School
David Burcham Elementary School
Carver Elementary School
Cesar Chavez Elementary School
Cleveland Elementary School
Dooley Elementary School
Edison Elementary School
Emerson Parkside Academy
Fremont Elementary School
Minnie Gant Elementary School
Garfield Elementary School
Gompers Elementary School
Grant Elementary School
Bret Harte Elementary School
Patrick Henry Elementary School
Holmes Elementary School
Kettering Elementary School
Starr King Elementary School
Lafayette Elementary School
Lincoln Elementary School
Longfellow Elementary School
Los Cerritos Elementary School
Lowell Elementary School
MacArthur Elementary School
Madison Elementary School
Mann Elementary School
McKinley Elementary School
Monroe Elementary School
Muir Academy
Naples Bayside Academy
Newcomb K-8 Academy
Nieto Herrera Elementary School
Oropeza Elementary School
Powell Academy for Success
Prisk Elementary School
Riley Elementary School
Roosevelt Elementary School
Signal Hill Elementary School
Smith Elementary School
Stevenson Elementary School
Tincher Preparatory School
Mark Twain Elementary School
Webster Elementary School
Whittier Elementary School
Willard Elementary School
Middle Schools
In Progress

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: June 2025
Projected Completion: April 2027
Supported by Bond Measure: E
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: June 2025
Projected Completion: Nov. 2026
Supported by Bond Measure: E
Learn More

Project Type: Campus Transformation Phase 2
Construction Began: August 2025
Projected Completion: 2028
Supported by Bond Measure: E + Q
Learn More
Upcoming

Project Type: Track & Field
Construction Begins: June 2028
Projected Completion: Nov. 2028
Supported by Bond Measure: E

Project Type: Track & Field
Construction Begins: June 2028
Projected Completion: Nov. 2028
Supported by Bond Measure: E

Project Type: Track & Field
Construction Begins: June 2028
Projected Completion: Nov. 2028
Supported by Bond Measure: E

Project Type: All-Weather Field
Construction Begins: June 2027
Projected Completion: Nov. 2027
Supported by Bond Measure: E

Project Type: Track & Field
Construction Begins: June 2027
Projected Completion: Nov. 2027
Supported by Bond Measure: E

Project Type: All-Weather Field
Construction Begins: June 2028
Projected Completion: December 2028
Supported by Bond Measure: E

Project Type: Track & Field
Construction Begins: April 2027
Projected Completion: August 2027
Supported by Bond Measure: E
Recently Completed

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: April 2022
Project Completed: December 2023
Supported by Bond Measure: E
Learn More

Project Type: Solar Canopy Installation
Construction Began: February 2026
Project Completed: April 2026
Supported by Bond Measure: Q

Project Type: Campus Transformation Phase 1
Construction Began: September 2024
Project Completed: July 2025
Supported by Bond Measure: E + Q
Learn More

Project Type: New Gymnasium
Construction Began: December 2023
Project Completed: August 2025
Supported by Bond Measure: K
Learn More

Project Type: Solar Canopy Installation
Construction Began: January 2025
Projected Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: April 2021
Project Completed: August 2022
Supported by Bond Measure: E
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: July 2023
Project Completed: August 2025
Supported by Bond Measure: E
Learn More

Project Type: New Locker Room
Construction Began: June 2022
Project Completed: August 2023
Supported by Bond Measure: K
Learn More

Project Type: Solar Canopy Installation
Construction Began: Dec. 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More
School Specific Projects
- Bancroft Middle School
- Franklin Middle School
- Hamilton Middle School
- Hoover Middle School
- Hughes Middle School
- Jefferson Leadership Academy
- Keller Middle School
- Lindbergh STEM Academy
- Perry Lindsey Academy
- Marshall Academy of the Arts
- Nelson Academy
- Rogers Middle School
- Stanford Middle School
- Stephens Middle School
- Washington Middle School
Bancroft Middle School
Franklin Middle School
Hamilton Middle School
Hoover Middle School
Hughes Middle School
Jefferson Leadership Academy
Keller Middle School
Lindbergh STEM Academy
Perry Lindsey Academy
Marshall Academy of the Arts
Nelson Academy
Rogers Middle School
Stanford Middle School
Stephens Middle School
Washington Middle School
High Schools
In Progress

Project Type: Phase 6 - New Gymnasium & Aquatic Center
Construction Began: August 2024
Projected Completion: December 2026
Supported by Bond Measure: K
Learn More

Project Type: New Classroom Building
Construction Began: July 2025
Projected Completion: August 2027
Supported by Bond Measure: E
Learn More

Project Type: Phase 5B - Athletic Fields & Visitor Bleachers
Construction Begins: July 2026
Projected Completion: August 2027
Supported by Bond Measure: K
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: January 2025
Projected Completion: Sept. 2027
Supported by Bond Measure: E
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: June 2025
Projected Completion: Dec. 2027
Supported by Bond Measure: E
Learn More
Upcoming

Project Type: Natatorium Repurposing
Construction Begins: Sept. 2027
Projected Completion: August 2028
Supported by Bond Measure: E
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Begins: June 2026
Projected Completion: Dec. 2027
Supported by Bond Measure: E
Learn More

Project Type: New Aquatic Center
Construction Begins: June 2027
Projected Completion: Dec. 2028
Supported by Bond Measure: K
Learn More

Project Type: All-Weather Field
Construction Begins: June 2026
Projected Completion: February 2027
Supported by Bond Measure: E
Learn More

Project Type: Transformation
Construction Begins: November 2027
Projected Completion: August 2031
Supported by Bond Measure: Q
Learn More

Project Type: Natatorium Repurposing
Construction Begins: June 2027
Projected Completion: Dec. 2027
Supported by Bond Measure: Q & K
Learn More

Project Type: Athletic Field Improvements
Construction Began: Sept. 2026
Projected Completion: August 2027
Supported by Bond Measure: E
Learn More
Recently Completed

Project Type: Solar Canopy Installation
Construction Began: Nov. 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: New Aquatic Center
Construction Began: November 2023
Project Completed: July 2025
Supported by Bond Measure: E
Learn More

Project Type: Phase 5A - Stadium
Construction Began: May 2024
Project Completed: August 2025
Supported by Bond Measure: K

Project Type: New Aquatic Center
Construction Began: June 2023
Project Completed: August 2025
Supported by Bond Measure: K
Learn More

Project Type: Bleacher Replacement
Construction Began: Oct. 2020
Project Completed: Nov. 2024
Supported by Bond Measure:
Learn More
School Specific Projects
- Browning High School
- Cabrillo High School
- California Academy of Math & Science (CAMS)
- Educational Partnership High School
- Jordan High School
- Lakewood High School
- Long Beach School for Adults
- McBride High School
- Millikan High School
- Poly Academy of Achievers & Leaders (PAAL)
- Polytechnic High School
- Reid High School
- Renaissance High School
- Sato Academy of Math & Science
- Wilson High School
Browning High School
Cabrillo High School
California Academy of Math & Science (CAMS)
Educational Partnership High School
Jordan High School
Lakewood High School
Long Beach School for Adults
McBride High School
Millikan High School
Poly Academy of Achievers & Leaders (PAAL)
Polytechnic High School
Reid High School
Renaissance High School
Sato Academy of Math & Science
Wilson High School
K-8 & K-12 Schools
In Progress
Upcoming

Project Type: Heating, Ventilation & Air Conditioning
Construction Begins: July 2027
Projected Completion: March 2028
Supported by Bond Measure: E
Learn More

Project Type: Solar Canopy Installation
Construction Begins: July 2026
Projected Completion: July 2026
Supported by Bond Measure: Q
Learn More

Project Type: All-Weather Field
Construction Begins: June 2029
Projected Completion: Nov. 2029
Supported by Bond Measure: E
Learn More

Project Type: All-Weather Field
Construction Begins: June 2029
Projected Completion: Nov. 2029
Supported by Bond Measure: E
Learn More

Project Type: All-Weather Field
Construction Begins: June 2026
Projected Completion: Nov. 2026
Supported by Bond Measure: E
Learn More
Recently Completed

Project Type: Baseball Field
Construction Began: September 2023
Project Completed: October 2025
Supported by Bond Measure: E
Learn More

Project Type: Heating, Ventilation & Air Conditioning
Construction Began: June 2024
Project Completed: January 2025
Supported by Bond Measure: E
Learn More

Project Type: Campuswide Renovation & Heating Ventilation and Air Conditioning
Construction Began: January 2022
Project Completed: December 2023
Supported by Bond Measure: E
Learn More

Project Type: Solar Canopy Installation
Construction Began: August 2025
Project Completed: April 2026
Supported by Bond Measure: Q
Learn More

Project Type: All-Weather Field
Construction Began: June 2024
Project Completed: October 2024
Supported by Bond Measure: E
Learn More
School Specific Projects
- Browning High School
- Cabrillo High School
- California Academy of Math & Science (CAMS)
- Educational Partnership High School
- Jordan High School
- Lakewood High School
- Long Beach School for Adults
- McBride High School
- Millikan High School
- Poly Academy of Achievers & Leaders (PAAL)
- Polytechnic High School
- Reid High School
- Renaissance High School
- Sato Academy of Math & Science
- Wilson High School
Browning High School
Cabrillo High School
California Academy of Math & Science (CAMS)
Educational Partnership High School
Jordan High School
Lakewood High School
Long Beach School for Adults
McBride High School
Millikan High School
Poly Academy of Achievers & Leaders (PAAL)
Polytechnic High School
Reid High School
Renaissance High School
Sato Academy of Math & Science
Wilson High School
Administrative Sites
In Progress
Upcoming
Recently Completed
School Specific Projects
Accordion
Bethune Head Start
Current Projects
Current Projects
CAMPUSWIDE RENOVATIONS
Addams' comprehensive renovations will include new energy-efficient heating, ventilation and air conditioning system for the school’s existing permanent buildings and select priority projects from LBUSD’s 2022 Facility Master Plan.
Additional campus improvements include:
- New audiovisual systems with overhead projectors & screens
- New flooring, ceilings, lighting and paint
- Window replacement or repair
- Accessibility upgrades
- Fire alarm system upgrades
- Other renovations